Hillary’s Boat Harbour

Case Study
WA Limestone, in a joint venture with Italia Stone Group, constructed a 2 kilometre seawall, which included the supply, transport and installation of 800,000 tonnes of limestone core and armour.

Hillary’s Boat Harbour Development

WA Limestone, in a joint venture with Italia Stone Group, constructed a 2 kilometre seawall, which included the supply, transport and installation of 800,000 tonnes of limestone core and armour.

The majority of the rock was supplied from the company’s Mullaloo quarry, and at the time the project represented the largest undertaken by WA Limestone.

  • Cilent

    State Government

  • Location

    Hillarys

  • Duration

    1986-87

  • Value

    $12M